Page 1 of 3 123 LastLast
Results 1 to 10 of 25

Thread: Shopbot Assembly Photos

  1. #1
    Join Date
    Nov 2007
    Location
    Stoddart's Ltd. Company, Cumming GA
    Posts
    16

    Default Shopbot Assembly Photos

    The posts and pictures on the forum were very helpful for our Shopbot assembly. For what it is worth, here are some pictures of how our Shopbot went together. Hopefully, they'll be of some help to others putting their machines together.

    Here's where it all started - the empty space in our workshop.


    28299.jpg

    The starting point was assembly of the frame. Here's the legs and the sides coming together.


    28300.jpg


    28301.jpg


    28302.jpg

    Here are all of the cross members assembled, and the leveling and installation of the rails. While it helped that we stared out with a level floor, leveling the frame wasn't too difficult following the instructions in the manual.


    28303.jpg


    28304.jpg

    Here's the installation of the XY and Z cars on the rails.


    28305.jpg


    28306.jpg

    Our machine came with the plexiglass cable guide, but following the lead of others on the forum, we used cable carriers. These were purchased from McMaster Carr. (Thanks to Gary Campbell for model number information he posted on the forum). The upper cable carrier was mounted with some pretty simple home-made aluminum brackets. The x-axis lower cable carrier is also mounted to aluminum brackets, but also has a plexiglass plate for support.


    28307.jpg


    28308.jpg

    Here's the wiring of the cable carriers.


    28309.jpg

    We mounted our control box and VFD to the wall next to the Shopbot. This was pretty simple (except that the mount locations were not optimized for normal stud spacing). Based on other forum posts about heat, our mounting concept (white painted 2x4's) left plenty of airspace behind the boxes. We were originally a little worried about having enough wire to run from the machine to the boxes, but everything worked out OK.


    28310.jpg

    Here's how the machine looked with all of the wire run through the cable carriers.


    28311.jpg


    28312.jpg

    Here's the external view of the wiring to the boxes. The gray plastic box under the control box is where we coiled all of the excess wire.


    28313.jpg

    Here's a picture of the interior of the control box completely wired with the power feeds and control lines, and a photo of the wires coming out of the control box.


    28314.jpg


    28315.jpg

    Now, this is where we departed from the norm -- we are using an Apple i-Mac to run the shopbot. Here's the mounting of the i-Mac on the wall. It's an elegant solution -- the i-Mac has a big screen and the computer all in one package -- plus an industrial quality wireless keyboard. This is a 24" 2.8GHz model. It easily mounts to the wall using an Apple VGA mount kit and a VGA wall mount.


    28316.jpg

    With the machine wired, the next step was the vacuum table. Here is the first layer of the table getting ready to be bolted down. This is a sheet 3/4 inch 5x9 MDF. While we would have rather not used MDF, this was the best solution we could find for our 96x60 machine. (Our workshop is pretty dry, so hopefully it won't turn into "rice krispies" as Bill Palumbo said at recent Camp Shopbots).


    28317.jpg

    Here's the plenum layer being glued on. We attempt anything fancy for this process -- just used a lot of clamps and weights to hold the material down. This is another sheet of 3/4 inch 5x9 MDF.


    28318.jpg

    Here's the first time the machine cut anything -- the plenum board. This is a photo of the cutting just starting.


    28319.jpg

    With that, we breathed a sigh of relief that the i-Mac would really run the Shopbot. After reading forum posts about this and not getting enthusiasm for Apple from Shopbot training class, we were a little nervous that this would work. Here's proof that it does -- Shopbot control software running on the Mac. We're using Parallels software to run the PC files. This solution really works well for us. We've got several Mac's networked in our home and office. When we finish a design file in the office, we are easily able to move the design file to the workshop Mac on the network. Plus we've discovered some other interesting features using one of the new dual-core processor Macs. For example, i-Macs have a built in camera that shows real time pictures in a video conference over the network or over the web. Because we are able to run Shopbot control software and Mac programs simultaneously, we can point the camera at the Shopbot and watch/hear the Shopbot cutting files. Overall, the Mac works great. The screen is big and visible, and it has a great wireless keyboard and wireless mouse that make it really convenient to run the machine.


    28320.jpg

    Here's what the plenum looked like after it was cut. Although we really liked some of the more elegant plenum ideas on the forum, we decided to keep it simple on version 1. We set up 7 zones. Five zones were set up to hold down normal 4x8 sheet goods. The other two zones -- which use the extra foot of the 96x60 machine are contemplating that we'll use the machines for board lumber. The 4x8 area was broken into 5 zones to create one 2x2 zone in front where we could run smaller pieces.


    28321.jpg

    To seal the plenum, we sprayed it with 5 coats of polyurethane floor finish. Here's the machine taped off for spraying and the final finish.


    28322.jpg


    28323.jpg

    We tried to stay simple with our vacuum piping design. One Fein vac runs the front of the table and one runs the back of the table with an ability to connect both Fein vacs together to run specific zone. We mounted the piping on an aluminum angle on the side of the machine -- which kept the front of the machine very clean and made runs to the table simple.


    28324.jpg


    28325.jpg


    28326.jpg

    Here's how the piping looks under the table.


    28327.jpg

    The vacuum piping connected to the plenum table mostly by a friction fit. With the Shopbot precision cut holes and a lot of polyurethane, plastic piping fit very tightly in the plenum holes. We also sealed around the bottoms with silicon. Here's how the plastic piping looks coming through the plenum table.


    28328.jpg


    28329.jpg

    Next was installing the spoilboard and surfacing both sides. For the spoilboard we used two pieces of lightweight MDF -- with a seam that matched our plenum design. The first attempt at surfacing the spoilboard was a disaster -- we tried to do it with no clamps and just vacuum. Unfortunately, as we cut the skin off of the first side, the MDF sheet started releasing its internal stresses and started curling. We successfully turned that sheet into mostly sawdust. For our next attempt we used clamps at the corners. That solved the problem. Plus it also taught us about safe Z clearance heights when we cut through our first clamp. Here's a picture of the spoilboard being surfaced with the surfacing bit.


    28330.jpg

    This worked well -- our resulting surface was flat and smooth on both sides. The edges of the table including the spoilboard were sealed with multiple coats of polyurethane and gray epoxy paint prior to surfacing the final side. The spoilboard was glued down with a lot of silicon sealer/adhesive. We used the vacuum to hold down the spoilboard -- using some wax paper on top of the spoilboard to create enough vacuum.

    Here's the final product.


    28331.jpg

    We made one last modification -- to the Fein vacs. We experienced vacuum leaks connecting hoses to the orange Fein bodies. So, using an idea from the forum, as our first Shopbot project, we built custom bases for the Fein heads. Here are the new Fein bases being cut out on the machine from one sheet of MDF:


    28332.jpg

    Here's the base of the assembled box -- sprayed with multiple coats of polyurethane and then the interior coated with epoxy paint.


    28333.jpg

    The top of the box was built to fit up inside the Fein head and provide a solid seal.


    28334.jpg

    This is the completed Fein stand -- a photo of the stand and a photo with the Fein head installed.


    28335.jpg


    28336.jpg

    Here are the Feins attached to the vacuum piping.


    28337.jpg


    28338.jpg

    That's it. Here are overall photos of the final machine installation.


    28339.jpg


    28340.jpg


    28341.jpg

    Thanks again for all the forum users who posted information that helped us get our machine started.

  2. #2
    Join Date
    Apr 2007
    Location
    Marquette, MI
    Posts
    3,388

    Default

    Alison...
    Nice neat clean job. Good pictures, too. Now that you have ruined a sheet of material, cut a clamp, all you have to do is break a few bits and you are initiated!!
    Gary

  3. #3
    Join Date
    Jan 2004
    Location
    Novato CA
    Posts
    223

    Default

    WOW! That's one heck of a first post! Well done.

  4. #4
    Join Date
    Oct 2000
    Location
    Toms River, New Jersey
    Posts
    2,091

    Default

    Alison,
    GREAT pictures!!!, Great Info!!!, and GREAT Posting !!! Thanks for putting the time in to assemble all of that.....Hope we can either reference the posting, or just transfer the entire posting to the WIKI(?)

  5. #5
    Join Date
    Nov 2007
    Location
    Stoddart's Ltd. Company, Cumming GA
    Posts
    16

    Default

    Bill: Feel free to use the pictures and information any way you feel would be of value.

  6. #6
    Join Date
    Feb 2008
    Location
    Carving Artists - Martin & Martin, Las Vegas NV
    Posts
    10

    Default

    very impressive, thanks for taking the time to post all of that...where did you find the plans for plenum

  7. #7
    Join Date
    Nov 2003
    Location
    Remembrances, Fayetteville Texas
    Posts
    300

    Default

    Outstanding set up of your machine. BTW you have email.

  8. #8
    Join Date
    Apr 2006
    Location
    Alchemy CNC Studio, Austin Texas
    Posts
    601

    Default

    Fantastic job Allison. & welcome to the community. If Gary Campbell tells you "Good job" then you can definitely be proud of your work. I'm designing on a Mac on Parallels, it seems to run Windows better than Windows, as Gene Buckle says, "Linux for servers, Macs for design, and Windows for Solitaire" Again great work, now I'll copy your design for the vac table if you dont mind - Neville

  9. #9
    Join Date
    May 2006
    Location
    Ontario Canada
    Posts
    575

    Default

    Nice Setup Alison. Would love to see pics of the rest of your shop. It looks very clean, tidy and impressive.
    Glen

  10. #10
    Join Date
    Dec 2007
    Location
    Duncan, British Columbia, Canada
    Posts
    230

    Default

    Alison,
    Great pictures. Thanks for taking the time to share them with us. I am scheduled to received my Bot in April and will be referring back to these pictures often as a reference and as an 'excitement generator' until mine Bot arrives.

    I agree with Glen. Your shop looks great.

    Scott

Similar Threads

  1. Ninety ShopBot-Vectric Project Photos
    By mtylerfl in forum Folder 2016
    Replies: 0
    Last Post: 08-09-2016, 06:59 PM
  2. shopbot assembly problem
    By Michaelodunk in forum ShopBotter Message Board
    Replies: 4
    Last Post: 04-08-2012, 10:51 PM
  3. ShopBot Dust Skirt assembly
    By harryball in forum Archives2006
    Replies: 11
    Last Post: 09-13-2006, 09:50 PM
  4. Photos of Signs done with ShopBot
    By Mayo in forum Archives2006
    Replies: 3
    Last Post: 06-12-2006, 11:12 PM
  5. Assembly Instructions for ShopBot Steel Table
    By threadfx in forum Archives - thru 2002
    Replies: 1
    Last Post: 04-06-2001, 12:47 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •