    Hello,
    I am moving my machine soon and plan on using Josh's plans to build a new vacuum box. My question is, he plumbed all the motors into the same line with gate valves. Would it be more beneficial to plumb each of the 4 to a separate quadrant of the table (96x48) then maybe have a crossover between to motors in case of a failure? Or plumb them all together like he had? Why or why not?

  2. #2
    Join Date
    Dec 2008
    Location
    , Richmond Tx
    Posts
    1,091

    Default

    I have done several where I put cut off electrical switches on some of the pumps. No valves used and just turn on the sections you need at the time. Everyone likes something different, but it's easy, cheap, and works fine.
    Kenneth

  3. #3
    Join Date
    May 2014
    Location
    MA
    Posts
    611

    Default

    You can get sewer back flow prevention valves too that will automatically close on any motors that are turned off. That’s what I did on my setup back when I had it.

  4. #4
    Join Date
    Dec 2015
    Posts
    51

    Default

    Quote Originally Posted by EricSchimel View Post
    You can get sewer back flow prevention valves too that will automatically close on any motors that are turned off. That’s what I did on my setup back when I had it.
    I may have done a bad job explaining the question. I’m wondering if it’s better to have each pump going to the whole table like josh did, or have each pump plumbed directly to a single quadrant.

  5. #5
    Join Date
    Dec 2008
    Location
    , Richmond Tx
    Posts
    1,091

    Default

    I did per quad with electrical swithes to use the areas needed
    Kenneth

  6. #6
    Join Date
    Dec 2015
    Posts
    51

    Default

    Quote Originally Posted by ken_rychlik View Post
    I did per quad with electrical swithes to use the areas needed
    Hows it working? Im leaning towards doing it that way but have closable crossovers so if I have a failure i can run a half table with a single pump